Roadwork
Route | Section | Date of work | Type of work | Obstacles | Comments |
---|---|---|---|---|---|
Billy-Diamond Highway | KM 67.7 au KM 71.9 | September 9th, 2024 to may 7th, 2026 | Replacement of a set of culverts with a bridge at KM 69.8 | Complete closure and detour road in both directions. Reduced speed and presence of road signallers to alternate traffic. | Contact: Alain Andriamaro 873 995-2076 aandriamaro@sdbj.gouv.qc.ca |
Billy-Diamond Highway | KM 136 au KM 142 | July 30th to october 31th, 2024 | Culvert replacement | Diversion in both directions. Speed reduced to 50 km/h. Signallers to alternate traffic. | Contact: Alain Andriamaro 873 995-2076 aandriamaro@sdbj.gouv.qc.ca |
Billy-Diamond Highway | KM 380 to KM 460 | May 27th to October 15th, 2024 | Road resurfacing, culvert replacement, and guardrail replacement work. | Bumpy road in places Reduced speed in effect Posted speed (between 50 and 80 km/h) | Contact: Alain Andriamaro 873 995-2076 aandriamaro@sdbj.gouv.qc.ca |
Billy-Diamond Highway | KM 4 to KM 38 | May 27th to May 31st, 2024 | Mechanical clearing in the shoulder | Partial lane closure – Reduced width | Contact: Alain Andriamaro 873 995-2076 aandriamaro@sdbj.gouv.qc.ca |
Billy-Diamond Highway | KM 0 to KM 100 | July 2nd to 31st, 2024 | Clearing of undergrowth | Partial lane closure – Reduced width – Speed reduced to 70 km/h in places | Contact: Alain Andriamaro 873 995-2076 aandriamaro@sdbj.gouv.qc.ca |