This page presents the status of the roadwork on the road network served by the SDBJ. If you can not find the information you are looking for, do not hesitate to contact us: 819 638-8411 or rad@sdbj.gouv.qc.ca

For outsized load autorization requests, please send an email to the Infrastructures direction at: rad@sdbj.gouv.qc.ca

Road name Road section Duration Type of work Disruptions

Roadwork on the Chisasibi Road

Investment to replace 31 culverts on the Chisasibi Road.

This project is made possible thanks to funding from the Government of Canada and the Government of Quebec.

Chisasibi Road Km 0-90 July 1 to august 31 2022 Rockfilling of the culvert
  • Slow traffic
  • One lane of traffic alternating in direction
  • Traffic lights
  • Circulation on gravel 

 

Road name

Road section

Duration

Type of work

Disruptions

General information

Billy-Diamond Highway

Km 473

Km 466

Km 502

June 6 to July 20, 2022 Replacement of complex culverts
  • Slow traffic
  • One lane of traffic alternating in direction
  • Traffic lights
  • Circulation on gravel

Responsible:

Yves Nzosani
873 995-6275
ynzosani@sdbj.gouv.qc.ca

Km 419

Km 452

July 4 to September 25, 2022 Replacement of complex culverts
  • Slow traffic
  • One lane of traffic alternating in direction
  • Traffic lights
  • Circulation on gravel 

Km 473

July 3 to 10 Culvert replacement
  • Slow traffic
  • One lane of traffic alternating in direction
  • Traffic lights
  • Circulation on gravel
  • Detour route
Km 507-619 September 1 to 30, 2022 Paving work and granular recharging
  • Slow traffic
  • One lane of traffic alternating in direction
  • Traffic lights
  • Circulation on gravel 
Transtaïga Road Km 437-350 June 16 to July 3 2022 Granular recharging of the road
  • Slow traffic
  • Impediment in one lane

Responsible:

Joey Thériault-Gagnon
418 748-7777, ext 5229
jtheriault-gagnon@sdbj.gouv.qc.ca